The Abbey Hotel: Bath spa
Main MCCB change over panel
During an annual EICR it was recommended due to the age and condition that the MCCB panel was to be replaced in the basement area supplying 16 additional distribution boards which controlled multiple areas of the hotel. Due to hotels working 24hrs a day and the panel controlling all of the hotels power, careful consideration was taken into account working along side the management and maintenance teams to accomplish a safe and smooth transition.
The target was to shut down the power to the hotel and remove the old install and replacing with the new MCCB panel in a short amount of time to fall in line with the hotels requests and keeping disruptions to a minimum.
All possible outcomes were taken into account and contingencies were put in place in an unlikely occurrence that may prevent the power being re energised by having portable generators in place. 2 engineers were assigned to the task, both the operations manager and director were also in attendance.
Planning and preparation was key and building a structural frame and supports in advance were a key part of the change over due to the size difference of the existing and the new panel.
Quadrant and its team were able to achieve the task well within the agreed time limit with no issues and use of any back up generators.
Quadrant were also able to achieve completion of multiple remedial works throughout the hotel to bring the standards up to date and fall in line with current regulations BS7671 18th edition. This also includes further distribution board replacements controlling sensitive equipment. For example, data communication rooms and kitchens.
The hotel management were very pleased with the outcome- A massive well done to our engineers.
Visual Showcase
The Radisson Blu:
South Kensington, London. South Kensington's based Hotel is one of many in the Radisson Blu Edwardian Hotel chains.
Another project ticked off as part of Quadrants-Groups responsibility to maintain and upgrade to current BS7671 18th edition regulations while also keeping the hotels decor to its original interior as part of its authentic look.
Quadrant - Group carried an annual EICR and updated multiple remedials small and large throughout this 215 room Hotel, A team of engineers completed this particular job over the course of 6 weeks, Replacing over 75% of the distribution boards from the basement, reception and upper levels once again working alongside the hotels management and maintenance team insisting on a smooth transition which was achieved. Our team managed to overcome many obstacles during the period making sure the Hotel continues to function on a daily basis and the guests were not disrupted and enjoyed their stay.


Euston Square- London
(Formally the Grafton Hotel)
Euston Square is having an upgradeÂ
Quadrant- group we’re proud to achieve the 1st of many upgrades that Radisson Blu wanted to carry out to maintain and modernise its rooms.
Quadrant worked alongside designer's, Clients and crown interiors to achieve a bespoke finish.Â
Carrying out lux reports and applying extra from featured wall lights to concealed led lightingÂ
Additional power points, usb outlets and mist proof mirrors are all what the client requested while’s updating all electrics to current standard.Â
We are happy to announce we have secured the contract to carry out upgrades to over 300 rooms. Â
Another great job completed by our team.